Provided field surveying, design, construction plan and dedication plat
preparation and construction estimates for a 175-lot subdivision containing
12,500 feet of streets with waterlines, sanitary sewer and storm sewer.
The storm water management design includes a
three-pond secondary retention facility and one large storm water
retention pond which is a major design feature of this premiere
subdivision.
Construction Cost: $ 3,500,000
Design: 1993
Construction: 1994 - 1999